Bosaso Spring Water Sources Development — Phase II
The project “Bosaso Spring Water Sources Development Phase II if funded separately by EU (T05.EUTF-HoA-SO-23.04) and AICS (01/AICSNAIROBI/2023). The EU project aims to increase the size of the gravity adduction main to Bosaso from 5,000 cum/day to 7,500 cum/day and to build an irrigation system for 25 farms in Duud Shabeel, while the AICS project aims to further expand the trunk line up to 14,500 cum/day and additional activities for the farmers. The increase of the capacity of adduction main is necessary to exploit the abundant fresh water sources found in Dhuud Shabeel and surrounding springs.
Project Duration: EU 2022-2025 / AICS 2024-2025
Main activities
Ground water study
Engineering of water adduction main
Drilling of 9 exploration and productive boreholes
Construct adduction main with a capacity of 8,500 cum/day, long 21 Km
Construction of spring water uptake
Design and construction of two water systems for farmers
The technical studies and the works execution are carried out directly by Terre Solidali. Terre Solidali contributes to the project with the free use of several machineries and equipment
WATER
Projects Map
Funded by
Deliverables
Studies
Drilling wells
Flow lines construction
Trunk-line construction
Spring development
Water for Farmers
Pictures
Videos
Expertises
Equipment
Terre Solidali has the availability in Somalia of the following main equipment, instruments, machineries which can be used to carry out water studies:
Geophysical survey Hydro-geological survey Topographical survey Geotechnical and Boreholes