Bosaso Spring Water Sources Development — Phase I

The project Bosaso Spring Water Sources Development – Phase I has the objective to improve access to drinkable, affordable and adequate water service delivery in Bosaso.
The project aims to stenghthen the technical capacity of PWDA and the managerial capacity of GUMCO, the local PPP water supply company, to increase the water production and its quality through the study, development and the connection of the Duud Shabel springs located 28 km South East of Basosa.
The project is funded by EU, AICS.

Project Duration: 2018-2022

Main activities
  • Spring water study
  • Engineering of spring infrastructure, flow-line and trunk-line (total of 29 Km)
  • Construct the new water supply with a capacity of 5,100 cum/day
  • Fine-tune new PPP agreement
  • Assist PWDA to design pro-poor water tariff system and household water connection policy
The technical studies and the works execution are carried out directly by Terre Solidali. Terre Solidali contributes to the project with the free use of several machineries and equipment.

WATER
Projects Map

Funded by
Partner

Pictures

Expertises

Equipment

Terre Solidali has the availability in Somalia of the following main equipment, instruments, machineries which can be used to carry out water studies:

Geophysical survey
Hydro-geological survey
Topographical survey
Geotechnical and Boreholes